Getting Started With BUCSS

Why Not Plan From the Observed Effect Size?

A natural way to plan a new study is to take the effect size from a prior study and compute the sample size that would give, say, 80% power for an effect of that size. The trouble is that the prior effect size is rarely a trustworthy target, for two reasons.

  • Publication bias. The published literature is filtered. Studies that reached statistical significance are far more likely to appear in print than those that did not, so the effects you can read about are systematically larger than the effects that were actually run. Planning from a published estimate inherits that upward bias.
  • Uncertainty. Even without any filtering, a single study’s effect size is one draw from a sampling distribution. Treating that one number as if it were the population value ignores how much it could have come out differently.

Both forces push the same way: they make the prior effect look bigger and more certain than it is, so a study planned at face value tends to be underpowered.

The uncertainty piece is easy to underestimate. Even with no publication bias, the sample size needed for a target power is a nonlinear function of the effect size, so an overestimate reduces power (by planning too small a study) by more than an equally sized underestimate raises it (by planning a larger one). Symmetric error in the estimate therefore produces an asymmetric loss of power, which is why correcting for uncertainty, not just bias, matters.

What BUCSS Does

BUCSS (“Bias and Uncertainty Corrected Sample Size”) corrects the prior study’s effect before planning. It uses the prior study’s test statistic and design to build the likelihood of a truncated noncentral distribution, truncated because small, nonsignificant effects go unpublished (Taylor & Muller, 1996), then reads off a corrected noncentrality parameter at a chosen level of assurance. That corrected noncentrality parameter, rather than the face-value estimate, drives the sample size calculation for the planned study. The method is described in Anderson, Kelley, and Maxwell (2017).

library(BUCSS)

A First Example

Suppose a prior study used an independent samples t test with 20 participants per group and reported t = 3.00. We want to plan a new study with 80% power, and we want 80% assurance, that is, we want the realized power to reach or exceed 80% in 80% of replications.

result <- ss_buc_independent_t(t_observed = 3, n = 20, alpha_prior = .05,
                         alpha_planned = .05, assurance = .80, desired_power = .80)
result
term value
necessary_n_per_group 130
total_N 260
actual_power 0.801
ncp_adjusted 1.11
t_observed 3
n 20
alpha_prior 0.05
alpha_planned 0.05
assurance 0.8
desired_power 0.8

Design: Independent t test; Sample size unit: per group; Largest supportable assurance: .90

The correction calls for 130 participants per group, far more than a face-value calculation from t = 3.00 would suggest.

Reading the Result

Every ss_buc_* function returns a tidy object shaped like the result tables in the DMAR package: term/value rows holding the design results first (the necessary sample size, named for its unit; the implied total sample size where the unit is per group or per cell; the achieved power at the returned size; and the bias and uncertainty adjusted noncentrality parameter), followed by rows echoing the planning inputs, so the assumptions travel with the result. The print method shows the aligned table and closes with the design, the unit, and the largest assurance the prior result can support. Because the object is an ordinary data.frame underneath, you can pull any quantity out directly:

result$value[result$term == "necessary_n_per_group"]
#> [1] 130
result$value[result$term == "ncp_adjusted"]
#> [1] 1.105023

The unit the sample size is counted in depends on the design (per group, per cell, number of pairs, or total): the size row is named accordingly (necessary_n_per_group, necessary_n_per_cell, or necessary_N), and the unit also travels on the object so you never have to guess:

attr(result, "sample_size_unit")
#> [1] "per group"

For programmatic use the broom verbs give the convenient views, exactly as in the DMAR package: tidy() returns the compact estimate view (the sample size and its achieved power), and glance() returns the one-row wide view with every quantity and echoed input as a column.

tidy(result)
#>          term estimate     power
#> 1 sample_size      130 0.8014476
tidy(result)$estimate
#> [1] 130
glance(result)
#>   necessary_n_per_group total_N actual_power ncp_adjusted t_observed  n
#> 1                   130     260    0.8014476     1.105023          3 20
#>   alpha_prior alpha_planned assurance desired_power             design
#> 1        0.05          0.05       0.8           0.8 Independent t test
#>   sample_size_unit df_effect df_error assurance_ceiling
#> 1        per group         1      258         0.9050734

For a manuscript’s method section, planning_sentence() writes the sentence:

planning_sentence(result)
#> [1] "A planned study with 130 participants per group (total N = 260) attains 80% power with 80% assurance, after correcting the prior study's result for publication bias and uncertainty."

The Replication Example

When the prior study has unequal group sizes, you can pass both. Here a prior study reported t = 3.00 with group sizes of 50 and 55, and we ask for 90% assurance:

ss_buc_independent_t(t_observed = 3, n = c(50, 55), alpha_prior = .05,
               alpha_planned = .05, desired_power = .80, assurance = .90)
term value
necessary_n_per_group 1485
total_N 2970
actual_power 0.803
ncp_adjusted 0.526
t_observed 3
n_1 50
n_2 55
alpha_prior 0.05
alpha_planned 0.05
assurance 0.9
desired_power 0.8

Design: Independent t test; Sample size unit: per group; Largest supportable assurance: .93

The corrected plan calls for 1485 per group, a vivid illustration of how much publication bias and uncertainty can inflate the sample size needed for a dependable replication. Anderson et al. (2017) quoted 1482 for this example under the original grid-search method; as of BUCSS 2.0.0 the adjusted noncentrality parameter is found by direct root finding, which gives 1485.

The Function Family

BUCSS covers a range of designs, one function per analysis. Each summarizes the prior study with a single test statistic plus the design.

Function Analysis Prior statistic
ss_buc_independent_t (alias ss_buc_smd) independent t test / standardized mean difference t_observed
ss_buc_paired_t (alias ss_buc_smd_paired) dependent (paired) t test t_observed
ss_buc_one_way_anova one-way between-subjects ANOVA F_observed
ss_buc_factorial_anova two-way between-subjects ANOVA F_observed
ss_buc_factorial_anova_general between-subjects ANOVA, any factors or contrast F_observed
ss_buc_rm_anova within-subjects ANOVA (one or two-way) F_observed
ss_buc_rm_anova_general within-subjects ANOVA, any factors F_observed
ss_buc_mixed_anova split-plot (mixed) ANOVA F_observed
ss_buc_mixed_anova_general split-plot ANOVA, any factors F_observed
ss_buc_reg_coef single regression coefficient t_observed
ss_buc_R2 omnibus model R-squared F_observed
ss_buc_reg_joint joint test of a subset of predictors F_observed

See vignette("worked-examples", package = "BUCSS") for one worked example of each, vignette("understanding-assurance", package = "BUCSS") for how the assurance and alpha_prior settings shape the correction, vignette("reading-output", package = "BUCSS") for the print, tidy(), and glance() views of the result, and vignette("planning-replications", package = "BUCSS") for a worked demonstration of why a literature of underpowered studies misleads and how the correction repairs the replication sample size.

References

Anderson, S. F., & Kelley, K. (2024). Sample size planning for replication studies: The devil is in the design. Psychological Methods, 29, 844–867. https://doi.org/10.1037/met0000520

Anderson, S. F., Kelley, K., & Maxwell, S. E. (2017). Sample-size planning for more accurate statistical power: A method adjusting sample effect sizes for publication bias and uncertainty. Psychological Science, 28, 1547–1562. https://doi.org/10.1177/0956797617723724

Taylor, D. J., & Muller, K. E. (1996). Bias in linear model power and sample size calculation due to estimating noncentrality. Communications in Statistics: Theory and Methods, 25, 1595–1610.